The following presents a list of all the tasks to be developed throughout the project. Additionally, there are tabs available where one can view the board with the status of the activities, the timeline, and in each table labeled "Week," only the tasks planned for that specific period are listed.
In general, it is estimated that each team member will contribute an average of 87 hours. Thus, the total estimated time for the project is 436.8 hours.
In the event of discrepancies with the SUM at the end of the main table, it is important to note that the tasks: Technical Report, Final Presentation, Final Video and Meeting for task redistribution are included in the individual contribution calculation for each member, but they are only counted once in the overall total. Therefore, we have:
353.6+(6.5×4)+(6.5×4)+(6.5×4)+(1.3x4)=436.8h